24th – 25th March 2007: Work completed on 56040

1) Both ‘A’ and ‘B’ side battery boxes cleaned out, rubbed down and repainted white.
2) All four battery box trays removed, rubbed down and repainted white
3) Both battery box retaining bars removed, rubbed down and repainted white.
4) Both battery box doors removed, rubbed down and repainted white internally.
5) Six spare battery cells removed from the 20ft ISO container, and placed in the Arcon, to replace other defective battery cells
6) Both compressors stored outside, are now stored in the goods shed.
7) Both ‘A’ and ‘B’ side underframe areas that house the compressor, cleaned, rubbed down and repainted black.
The following jobs are to be completed by the end of Saturday 31st March:-

1) Shot blast all four battery box side clamps (to be done at work).
2) All four battery box side clamps to be repainted white.
3) Both battery box doors to be repainted black externally.
4) Replace all nuts, sets screws, bolts, washers and split pins with new items.

So on Sunday 1st April both battery boxes can be completely reassembled, ready to receive the battery cells when they are ready.